Survey steps and timeline

Timelines follow the Department of Lands' public guide to boundary, subdivision and merging surveys by private surveying offices. RANGWAD tracks every job against these numbers.

35–45 days

The private surveying office's part, from filing the application

35 days

Total standard time for the steps the private office handles

Free

RANGWAD monitors each surveyor's work under Department of Lands rules

  1. Sign the contract

    Once you confirm, the private surveying office signs a contract with you, counted from the day RANGWAD approves the job.

    Private surveying office
    2 daysStandard time
  2. File the survey application

    File the boundary, merging or subdivision application at the Land Office. You can authorise someone to file for you.

    Client / authorised representative
    1 dayStandard time
  3. Land Office issues the survey appointment

    The office shows the contract to receive the survey documents and agrees the survey date with the administration section.

    Land Office
    4 daysStandard time
  4. Collect neighbour notices and map records

    The office collects notices for neighbouring owners and copies of map records (Ror.Wor.Mor.) from the Land Office.

    Private surveying office
    1 dayStandard time
  5. Notify neighbouring owners

    Neighbouring owners are notified to attend and witness the boundary on the survey date.

    Land Office
    15 daysStandard time
  6. Survey day

    The private surveyor surveys on the appointed date, within 22 days of the appointment notice, places boundary markers and has neighbours certify the boundary.

    Private surveying office
    22 daysStandard time
  7. Submit the survey report

    The office manager checks and signs the result, then submits the report to the Land Office survey section.

    Private surveying office
    7 daysStandard time
  8. Land Office checks the result

    The survey section checks the result against regulations, proposes it to the land officer and passes it to the registration section.

    Land Office
    6 daysStandard time
  9. Corrections (if any)

    If the Land Office asks for corrections, the private office must complete them.

    Private surveying office
    3 daysStandard time
  10. Prepare the title deed

    The Land Office prepares the new title deed from the survey result.

    Land Office
    4 daysStandard time
  11. Register and receive the deed

    The Land Office calls the applicant to register and prepares the subdivision application, contract or agreement.

    Land Office
    45 daysStandard time
Timelines can be extended, for example if the survey date moves, neighbours change, a boundary is disputed, not all neighbours certify the boundary and must be notified again with at least 30 days' notice, or the applicant cancels. Every change appears on your tracking page.

Find out what your job costs with a free quote